Dinogirl 2024 年 7 月 9 日 下午 9:05
Gathering resources keeps cancelling itself
This only seems to be happening with ore and rocks. Whenever I gather ore or rocks, or place something to be constructed on ore or rocks, after a few seconds the ore and rocks auto cancel their gathering, stopping what I'm building from being built.
I have to sit there with the gather all resources tool and constantly reapply it the resources can be removed.
< >
正在显示第 1 - 4 条,共 4 条留言
cobra_overseergames 2024 年 7 月 11 日 上午 3:25 
Ok, thanks for this report, we will check it out and see if we can fix this before next update.

And just to be clear, you would like if the builders automatically picked up all the ore if you chose to build on top of it, right?
Dinogirl 2024 年 7 月 11 日 上午 4:59 
引用自 cobra_overseergames
Ok, thanks for this report, we will check it out and see if we can fix this before next update.

And just to be clear, you would like if the builders automatically picked up all the ore if you chose to build on top of it, right?
yes, the builders picking up the ore if chosen to build on it would help speed up the construction, thank you! keep up the good work, really enjoying your game!
cobra_overseergames 2024 年 7 月 12 日 上午 6:34 
Ok so I checked right now if it gives me the same problems, but everything works...

So can you please send us your files to our support mail so we can see what is the problem?
Send your save game file and your PatronLog.txt file to support@patronthegame.com with your nickname and you explaining what is the problem in the mail so we know what to look for.

We do hope we can get to the bottom of this since we can't recreate the bug on our own.
achdoormo 2024 年 8 月 16 日 上午 1:10 
This happens for me intermittently but it seems to be a mid-game problem, has never happened in the early game. I suspect that it is related to the priority of job calls for the workers, like if they have tasks queued and you give them a gather order they refuse it. I could highlight 10 stone piles to collect and 8 will be cancelled immediately, implying that only 2 workers were idle at that moment. Of course the order should be queued instead of cancelled but sometimes that just does not happen.
< >